Boeing is leaning toward increasing production rates for the 737 and 777 families with decisions expected by mid-year, Boeing Commercial Airplanes President and CEO Jim Albaugh said yesterday. The current 737 build rate is 31.5 units per month and the company expects to make a decision in June on whether to raise it. Last week, Airbus announced it was taking the A320 rate to 36 per month from 34 as of December (ATWOnline, March 10).
Mar 18, 2010
Boeing agreed to pay Air India $145 million in compensation for the delay in its 787s, the Indian government announced. AI parent National Aviation Co. of India had requested $710 million. It has 27 787-8s on order and has seen first delivery pushed back from the originally scheduled May 2008 to April 2011.
Mar 18, 2010
US FAA is issuing an Airworthiness Directive this week mandating a software fix for autopilot flight director computers on 777s to prevent runway overruns on takeoff, Boeing confirmed. "Boeing had received operator reports of flight crews inadvertently engaging the autopilot while on the ground," the company told the
Mar 17, 2010
Air Berlin yesterday announced the cancellation of 10 firm 787 orders worth a combined $1.7 billion at list prices, along with five options, "to account for a change in market conditions and in order to meet. . .specific operative requirements."
Mar 17, 2010
AWAS delivered a fifth A330-300 to Singapore Airlines. Aircraft will serve Abu Dhabi, Jeddah, Male and Kuwait City beginning this month, with Fukuoka and Taipei added in April and Colombo in May.
Mar 16, 2010
FAA issued an emergency Airworthiness Directive calling for operators of 737-600s, -700s, -800s, -900s and -900ERs to inspect elevator tab control mechanisms following "severe elevator vibration" on a Ryanair 737-800 that made an emergency landing in Brussels this month.
Mar 16, 2010
Fourth 787 joined Boeing's flight test fleet and completed its first flight Sunday partially equipped with passenger cabin fittings. ZA003 departed Paine Field in Everett at 10:55 a.m. Sunday morning and landed at Boeing Field at 2:01 p.m. In addition to demonstrating that the interior meets certification requirements, ZA003 will be used to conduct tests on systems, noise performance, flight-deck operations, avionics, electromagnetic effects, high-intensity radio frequency response and ETOPS. ZA001 has completed 57 flights, ZA002 37 flights and ZA004 one flight. Total combined hr.
Mar 16, 2010
Second 747-8 freighter completed its first flight Sunday. Test Program Manager Andy Hammer said the aircraft "performed well" on a 2.5-hr. flight on which it reached an altitude of 27,000 ft. and an airspeed of 240 kt. before landing at Boeing Field. The second aircraft will conduct tests focused on community noise, environmental control systems and extended operation performance (ATWOnline, March 12).